Start Time - Lapsing of Building Consent

A building consent lapses if work does not commence within 12 months of the date of issue of the consent, therefore you must have started work before that date or any further time as allowed by Council, ie an Application should have been approved for an Extension of Time.

A building consent is considered commenced at the time of the first inspection.