23 Jan 2026
#INFRASTRUCTURE MATTERS
Please see the upcoming planned road closures that are scheduled to begin the week starting: Monday 26 January 2026 *Please note that adverse weather or unexpected delays can affect these dates.
Road Closure: Hall Street Service Lane, Timaru Port
Where: Hall Street Service Lane
When: From Friday January 23 2026 till Tuesday January 27 2026
Why: Pavement investigation
Road Closure: Alexandra Street, Temuka
Where: Alexandra Street, between Maude Street and Ormsby Street
When: From 6:00 am to 6:00 pm, Monday January 262026
Why: Overhead power maintenance
Road Closure: Kellands Hill Road, Timaru
Where: Kellands Hill Road from Pages Road to Washdyke Flat Road
When: The road will be closed daily between 7:00 am and 6:00 pm from Tuesday January 27 2026 to Friday January 30 2026
Why: Tree Removal
Road Closure: Nile Street, Timaru
Where: From Wai-Iti Road to #9 Nile Street
When: From 7:00 am Monday January 26 2026 to 5:00 pm Friday March 20 2026
Why: Underground power upgrade
Road Closure: Winchester Hanging Rock Road
Where: Between Hall Road and Rapuwai Road
When: Friday January 26 2026 to Monday February 2 2026
Why: Pavement Damage
Road Closed: Resurfacing Programme
The following roads/streets are scheduled for chip sealing during the week, with road closures in place while work is carried out.
In most cases, each site takes 1–3 days to complete, depending on the length of the road.
- Cain Street, Timaru
- Tasman Street, Timaru
- Cook Street, Timaru
- Beaumont Street, Timaru