Once you have received your Building Consent

Don't forget to book all your inspections at the correct time before proceeding with further building work.

All building work must be carried out in accordance with your approved building consent. If you wish to change some aspect of the project you must obtain an amendment to the building consent before the work is carried out.

If the work has not been done in accordance with the building consent the Building Advisor may issue a Notice to Fix or a site instruction notice stating what is required to be done.

A building consent shall lapse if work has not commenced within 12 months of the date of issue, unless a time extension has been granted.

When all work is completed you must make application for a Code Compliance Certificate provided all work is completed, documentation provided and fees paid.